Friday, May 7, 2010

5th Week Day 5

Task for this day is to Do Columns Marking for Entire Block of 12 floors.

Things done in morning:
  1. Check all the Columns in all floors
  2. Label all the Columns in Ground floor in different layer to ease up duplicating of label for usage later on. (Total of 447 ++columns labeled)
  3. As most of the column are interconnected with the floor above, The labelling of column will be same as the column below, which we can copy the label of the column named below to the floor above as long as it is at the some coordinate.
  4. Noted that the Modelling and Keyplan might not be the same for Architectural drawing and Engineering Drawing as Architectural Drawing tends to draw the Viewing Sight on plan view while engineering drawing will be on the cross section of that floor.

Things Done in Afternoon ~ Offwork:

  1. Continue do the Labelling of Columns and then do the printings of all 12 floors on A2 size paper.
  2. Acquired the loading on each column for all the floors from Inez
  3. Print out the loading on column for all floors for labelling of forces on the floor plan.
  4. Labelling of forces on floor plan will be done next week as time id not enough for all the biddings.