Friday, May 14, 2010

6th Week Day 3~5

Pile Check


Labelling of pile num and group on plan to ease up inspection work


Check the working load on pile


( Different group of piles have different loading, EG 250 sized pile might have capacity of 1800 while 300 have capacity of 2500. Then, according to the best ratio of strength and number of pile, we can determine the pile that we want to use accordingly)




Stump Marking


Check Drawing Detailing


Some drawings might not been drawn properly and the value or arrangement might be wrong, so it will be consultant work to check it.



Check Design calculation of pile cap whether the calculation method is correct and the correctness of its answer.